In order to implement the sustainable development strategy, vigorously carry out energy conservation and emission reduction, comprehensive utilization of resources, accelerate the promotion of new wall materials, promote the adjustment of the industrial structure of new wall materials, and product upgrades. According to the "Notice of the National Development and Reform Commission of the Ministry of Finance on Printing and Distributing the "Administrative Measures for the Collection and Use of the Special Fund for New Wall Materials" (Cai Zong [2007] No. 77) and the "Sichuan Provincial Department of Finance, Sichuan Provincial Department of Housing and Urban-Rural Development, the People's Bank of China Hangzhou Branch's Notice on Printing and Distributing the "Implementation Rules for the Management of the Collection and Use of the Special Fund for New Wall Materials in Sichuan Province" (Chuan Caizong [2012] No. 48) The required notice is as follows:
1. The construction unit applying for the refund of the special fund for new wall materials shall meet the following conditions:
(1) The special fund for new wall materials has been paid in full according to the building area of the house construction project.
(2) The construction project uses new wall materials recognized by the Hangzhou Wall Materials Innovation Building Energy Efficiency Office (hereinafter referred to as "Hangzhou Wall Materials Energy Saving Office") in accordance with the "New Wall Materials Catalog (2013 Edition)" (Annex 1) , The use ratio accounts for more than 80% of the total wall material consumption, and the wall materials that are banned by the state are not used; and the thermal insulation enclosure structure is processed in accordance with the building energy-saving design standards.
(3) The construction unit shall promptly notify the Hangzhou Wall Materials Energy Conservation Office for verification before the wall plastering and concealment treatment is not carried out after the completion of the wall of the construction project. The Hangzhou Wall Materials Energy Conservation Office will send personnel to the construction site to verify the use of wall materials within three working days and fill in the "Verification of Wall Materials Application Construction Site in Hangzhou" (Annex 2). Construction projects that have been plastered and concealed without verification shall not be refunded to the special fund for new wall materials paid.